As a part of their green energy initiative, Wonderla Hyderabad has now upgraded their solar power generation to 797 kWp Capacity

Wonderla Holidays Ltd, India’s largest amusement park chain upgraded their solar power plant at Hyderabad Park on July 13th, 2022, as a part of their green energy initiative. Mr Rajaram Reddy, DE Operations, TSSPDCL along with Mr. Madhu Sudhan. G, Park Head, Wonderla Hyderabad inaugurated the upgraded solar power energy unit.

Commenting on the initiative, Arun K Chittilappilly, Managing Director Wonderla Holidays Ltd said, “Understanding the power consumption of the business, Wonderla Holidays Ltd. installed solar panels at all the three parks, including the Hyderabad Park in 2016 when it launched. We have added more panels at the Hyderabad Park and with this upgradation, we aim to meet the daily power requirements for Park and Ride Operations through solar energy.”

Currently, a total of 2321 solar panels have been installed at the park, thereby reducing the heat inside the building and generating solar energy simultaneously.

Besides the Hyderabad Park, the Bangalore and the Kochi Park generate solar power for daily energy requirements like Ride Operations and Park power requirement.

Solar Power Generation Details Enclosed: –

 

Location Wonderla Holidays Ltd, Hyderabad

Parking & Admin Rooftop

Installed Capacity 797 kWp
Plant-1 Parking 500KW PV Module 310Wp Polycrystalline x 1613 No’s

Inverter 33KW x 15 No’s

No of Strings- 6 Strings/Inverter

Plant-2 Parking 227KW PV Module 450Wp Monocrystalline x 504 No’s

Inverter 50KW x 4 No’s

No of Strings- 7 Strings/Inverter

Admin Building 70KW PV Module 325Wp Polycrystalline x 204 No’s

Inverter 33KW x 02 No’s

No of Strings- 6 Strings/Inverter

Approximate Power Generation 3080 kWh/Day